Springvale landscape

Springvale

Operation By Centennial: 50% share (joint venture with SK Kores Australia Pty Ltd)

 

Commercial operations:

1992

Location:

Western Coalfields near Lithgow, NSW

Mining Method:

Underground (Longwall)

Markets:

Domestic and Export - Thermal coal

Status:

Operational

Coal extracted in 2013:

2.7 million tonnes per annum

Full production capacity:

4.5 million tonnes per annum

Remaining coal reserves:

49.5 million tonnes

Transportation:

Dedicated conveyors to domestic customers, rail to Port Kembla

Infrastructure:

Crushing house on site, coal preparation plant (at Western Main), overland conveyors

Main Content

Springvale is located in the western coalfields near Lithgow in New South Wales. Coal is produced using underground longwall mining methods and is transferred by conveyor to the surface facilities area, where it is either transported by dedicated overland conveyor to Mt Piper and Wallerawang power stations or processed for export at Centennial’s Western Main facility. Last year, the majority of coal produced was transported by train to Port Kembla for export to overseas customers.

This year, Springvale has reached a major milestone and celebrated 20 years of operation. The mine has a strong history of supporting the local community through sponsorship of local community organisations, schools, and events as well providing local job opportunities.

Community


Blasting Notifications

View all Springvale/Blasting Notifications documents

Community Consultation

View all Springvale/Community Consultation documents

Community Consultative Committee

A Community Consultative Committee (CCC) provides a forum for open discussion between representatives of the Company, community, council and other stakeholders on issues directly relating to the mine’s operations, environmental performance and community relations, and keeps the community informed on these matters.

Although not required under its current consent, Springvale requested endorsement from the Department of Planning and Infrastructure for the establishment of a community consultative committee.

Springvale now has a joint CCC with Angus Place. For information on the Community Consultative Committee please go to the Angus Place operations page or click on the link below.

View all Springvale/Community Consultative Committee documents

Community Complaints Register

The Springvale Community Information Hotline is (02) 6350 1640. A register of community complaints received by the mine can be viewed in the document below. There are currently no documents

View all Springvale/Community Complaints Register documents

Stakeholder Engagement Plan

View all Springvale/Stakeholder Engagement Plan documents

Development, Mining and Environment Approvals

The following document(s) relate to the mine’s operating and licence conditions.


Authorisations under the Mining Act

View all Springvale/Authorisations under the Mining Act documents

Consents and Approvals under the EP and A Act

View all Springvale/Consents and Approvals under the EP and A Act documents

Environment Protection Licence

View all Springvale/Environment Protection Licence documents

Environmental Protection and Biodiversity Conservation (EPBC)

View all Springvale/Environmental Protection and Biodiversity Conservation (EPBC) documents

Exploration

View all Springvale/Exploration documents

Environmental Assessments

Environmental Assessments (EAs) are an assessment of the environmental, social and economic benefits and impacts of a proposed project or modification to an existing project. EAs are regulated by the NSW Department of Planning and Infrastructure.


Environmental Assessments

View all Springvale/Environmental Assessments documents

Environmental Management

Approvals obtained to facilitate mining generally require management plans in consideration of various identified environmental impacts. These plans vary from operation to operation to reflect the operating conditions.


Environmental Management Plans, Strategies and Programs

View all Springvale/Environmental Management Plans, Strategies and Programs documents

Mining Operations Plan / Rehabilitation Management Plan

Mining operations in NSW are required, as a condition of an authorisation issued under the Mining Act, to conduct mining operations in accordance with a Mining Operations Plan (MOP) that has been approved by NSW Trade and Investment - Division of Resources and Energy.
The MOP describes the manner in which mining, processing, rehabilitation and reporting are to be undertaken with reference to Management Plans and Procedures. The MOP also establishes relationships to other approval and reporting requirements consistent with development consent, leases and licences.

View all Springvale/Mining Operations Plan / Rehabilitation Management Plan documents

Pollution Incident Response Management Plan

The Pollution Incident Response Management Plan has been developed to satisfy the requirements of the Protection of the Environment Legislation Amendment Act 2011 (POELA Act) which requires the preparation, implementation and publication of a Pollution Incident Response Management Plan.
The objectives of these plans are to provide guidelines and procedures for the effective control and reporting of pollution incidents to all relevant stakeholders.
Whilst personal contact details for the following document are available in the controlled on-site Pollution Incident Response Management Plan, they do not appear in this public document under provision of the Privacy and Personal Information Protection Act 1998.

View all Springvale/Pollution Incident Response Management Plan documents

Subsidence Management

Subsidence Management Plans (SMPs) are prepared by mining lease holders to consider the potential impacts of underground mining and identify measures to manage such impacts. SMPs may contain requirements for the avoidance of damage to particularly significant features, the mitigation of damage, or rehabilitation of subsidence related impacts.

View all Springvale/Subsidence Management documents

Environmental Reporting & Compliance

The following provides a summary of environmental monitoring data undertaken as required by Environment Protection Licences and Approvals. The purpose of this data is to provide the community with meaningful information on the performance of environmental controls.


Annual Reports

View all Springvale/Annual Reports documents

Environmental Monitoring Reports

View all Springvale/Environmental Monitoring Reports documents

Independent Environmental Audits

Independent Environmental Audits are undertaken regularly as a component of each mining approval. The audit is undertaken by a suitably qualified independent expert. The purpose of the audit is to independently assess the environmental performance of the mine and whether it is complying with the relevant requirements of its project approval, any relevant mining lease and environmental protection licence.

View all Springvale/Independent Environmental Audits documents

Transport Records

View all Springvale/Transport Records documents